Most custom home builders charge in one of two ways: a fixed price, or cost-plus, where you pay the actual cost of the work plus a builder’s fee. Trade cost guides commonly put that fee at about 10% to 20% of construction cost. The fee matters, but so does what it covers, and whether you can see the costs underneath it.
Updated November 2026. This guide explains each contract, what moves a builder’s fee, where the money goes and what to ask before you sign.
Key Takeaways
- Custom home builders typically charge through fixed price contracts or cost-plus contracts. One gives you budget certainty, the other gives you a view of the actual costs.
- Trade guides commonly put builder fees at about 10% to 20% of construction cost. Experience, complexity and location all move it.
- Lenders commonly advise a contingency of about 10% of project cost, or 20% if you act as your own general contractor.
- Ask to see the records. River Hills gives every client a dedicated project account, plus copies of bank statements, lien releases and line-item estimates.
Pricing Models for Custom Home Builders
Custom home builders typically charge using two main pricing models. Each has real advantages and real tradeoffs, and knowing them helps you pick the one that fits your project.
Fixed price contracts set a total project cost up front. Cost-plus contracts have you pay the actual costs of construction plus a builder’s fee. The key difference is that a fixed price is set before construction, while a cost-plus total moves with actual expenses.
Fixed Price Contracts
A fixed price contract sets the total cost of the project up front, which gives you certainty about your budget. The builder takes on the risk of cost overruns inside the agreed scope, so the builder has every reason to manage the project efficiently. That risk is usually priced in, so the first bid may run a little higher. Make sure the contract spells out the scope, the payment schedule, the warranty and how changes get priced, because anything outside the written scope can still cost extra.
Cost-Plus Contracts
With a cost-plus contract, you pay the actual costs of the project plus a builder’s fee. The main advantage is transparency: you can see detailed breakdowns of expenses and where your money is going. It suits people who want to be involved in the financial side of their build, and it leaves room for adjustments during construction.
The tradeoff is that the final total can move. Ask how the budget is tracked, what counts as a cost and whether any fees sit inside those costs.
There are two common versions. Cost-plus-a-fixed-fee keeps the builder’s fee unchanged for the agreed scope, which adds predictability. Cost-plus-a-percentage adds a set percentage on top of labor and materials, so the fee rises if the costs rise.
Key Factors Influencing Builder Fees
Trade cost guides commonly put builder fees at about 10% to 20% of total construction cost, and some put cost-plus fees as high as 25%. These are guides, not a survey, and fees vary with the builder’s experience, the complexity of the project and the location.
Experience and Reputation
Experienced builders often charge more because they anticipate problems before they become expensive. Ask about previous projects and talk to past clients. River Hills has been building in and around the Texas Hill Country since 2007, and our project managers are required, with rare exception, to visit the site every day work is going on.
Project Complexity
Complex projects take more planning, more coordination and more specialized trades, which can raise the fee. Larger homes and unique architectural features affect both the construction cost and the time your builder spends on the job. Ask how a builder estimates, so you know the budget is based on real prices.
Geographic Location
Labor rates, overhead and local rules all vary by area. In the Hill Country, the land itself matters too: rock, wells, septic systems and water-quality rules change what a builder has to plan and manage. Our guide to what it costs to build in New Braunfels goes through the local numbers.
Breaking Down Construction Costs

Knowing where the money goes helps you build an accurate budget, and a price per square foot alone can mislead you. The National Association of Home Builders’ 2024 cost survey gives a national average for the construction of a new home:
| Stage | Share of construction cost |
|---|---|
| Site work | 7.6% |
| Foundations | 10.5% |
| Framing | 16.6% |
| Exterior finishes | 13.4% |
| Major system rough-ins | 19.2% |
| Interior finishes | 24.1% |
| Final steps | 6.5% |
| Other | 2.1% |
That survey covers many kinds of homes and is a small sample, so treat it as a rough map. On rocky Hill Country land, site work and foundations can take a larger share. Soil testing, grading, tree removal and utility connections are the items most often missed in an early budget.
Materials and Finishes
Interior finishes are the largest slice in that survey, and they are where your choices move the budget most. Premium materials can raise both the material cost and the labor to install them. Balancing quality and cost room by room is usually the best way to protect the budget.
Labor Costs
Labor runs through every line of a budget. Wages vary by area and by trade, and skilled trades such as electricians and plumbers cost more than general labor. A builder with steady subcontractor relationships can plan around availability.
Permits and Inspections
Permit costs vary by city and county, so get the real number for your lot. In the 2024 survey, building permit fees averaged $7,640 nationally, or 1.8% of construction cost. Impact fees and utility fees can be much larger than the permit: in New Braunfels, utility impact fees alone can pass $25,000 on a newly platted lot. Various inspections are required at different stages, and some features such as pools can need their own permits. Lots outside city limits have their own county rules. Here is how permits work in Comal County.
Managing Unexpected Costs
Unplanned costs happen on custom builds. Common ones include problems found in the ground, products that become unavailable, special permits and engineering tests. A thorough contract review helps you avoid fees you did not expect.
Contingency Funds
The National Association of Home Builders says most lenders advise a contingency of 10% of project cost, raised to 20% if you are your own general contractor. Your lender may have its own rule, so ask early.
Change Orders
Change orders can raise costs and cause delays, especially late in the build. Changes are part of building a custom home, so the point is not to avoid them at all costs. The point is to know the price and the schedule effect before you approve one.
Financing Your Custom Home Build
Construction loans are the most common choice. They are short-term loans that cover the build, and you usually pay only interest during construction. Once the home is finished, the loan converts to a regular mortgage or gets paid off with one.
Construction Loans
Down payments vary a lot by program. FHA construction-to-permanent loans start at 3.5% and VA loans can require nothing down if the price does not exceed appraised value, though lenders can add their own rules. Federal rules for banks generally point to at least 15% equity on a residential construction loan, and banks and credit unions we checked ask for anywhere from 15% to 30%. Regional banks often know local builders, so they are worth a call. Talk to a lender before you settle on a budget.
Other Financing Options
Personal savings avoid interest payments. A home equity line of credit lets you draw funds as you need them, if you have enough equity in your current home. Each has its own tradeoffs, so ask your lender or financial advisor which fits you.
Choosing the Right Custom Home Builder
The builder you choose affects the quality and value of your home as much as the design does.
Research and Referrals
Local home builders associations can provide lists of builders in your region, and real estate agents and past clients can point you to reliable ones.
Interviewing Builders
Ask about experience with similar projects, how contracts and payment schedules work, and how unexpected issues get handled. Our list of questions to ask custom home builders is a good place to start.
Reviewing Contracts
A detailed contract should spell out the scope of work and the payment timeline, along with warranties and insurance. Ask for references from past clients as well.
How River Hills Handles the Money
Whichever contract you choose, you should be able to see where your money goes. Our Transparency Policy puts that in writing:
- Your project gets its own dedicated account, and customer funds are never mixed with other projects.
- You receive copies of bank statements, lien releases, line-item estimates and other documents relating to your home.
- River Hills does not accept kickbacks from vendors or subcontractors.
- You start with a preliminary estimate covering labor, materials, site work and selected features, and the budget gets revised as plans are finalized. Our Budget Cost Analysis builds it line by line.
Frequently Asked Questions
How much do builders charge to build a house?
It depends on the contract. Under a fixed price, the builder’s fee is built into one total price, so you may never see it as a separate number. Under cost-plus, you pay the actual cost of the work plus a fee, and trade cost guides commonly put that fee at about 10% to 20% of construction cost. A fixed fee is another option, where the dollar amount stays the same even if costs move. No single number is right for every project, because the size of the home, the complexity and the lot all change the work involved. Ask any builder for three things in writing: what the fee covers, what counts as a cost, and how changes get priced. River Hills starts with a preliminary estimate covering labor, materials, site work and selected features, then revises the budget as the plans and specifications are finalized.
How much do builders profit per house?
Across all kinds of new homes, builders reported an average profit of 11.0% of the sale price in the National Association of Home Builders 2024 cost survey, about $72,971 on an average sale price of $665,298. Overhead was another 5.7%. Those are national averages from a small survey that mixes many kinds of builders, and they are not the same thing as a custom builder’s fee. On a custom home you usually own the lot and hire the builder, so the question to ask is what the fee covers and whether you can see the costs underneath it. A fee on open books tells you far more than an average. At River Hills your project has its own dedicated account, and you receive copies of bank statements, lien releases and line-item estimates, so you can verify where the money went.
Do custom homes cost more?
Usually, yes, when you compare the price per square foot, and there are good reasons. A home built for sale spreads one plan and one set of selections across many lots, while a custom home is designed for one family and one piece of land. Census figures for 2025 show the difference in time alone: the average contractor-built home in the South took 9.0 months from start to completion, against 5.5 months for a home built for sale. Land matters as well. On Hill Country acreage, rock, wells, septic systems and long driveways can add real cost that a finished subdivision lot has already absorbed. What you get for it is a home that fits your lot and your family, and a chance to spend where it matters to you. Our guide to custom homes and tract homes walks through the tradeoffs.
What is the difference between fixed price and cost-plus contracts?
A fixed price contract sets one total cost up front. A cost-plus contract pays the actual costs of the work plus a fee, so the final total can move. Fixed price offers more budget certainty, and cost-plus offers more visibility into the actual costs.
What are contingency funds and why are they important?
A contingency is money set aside for costs nobody could see coming. Most lenders advise about 10% of project cost, or 20% if you act as your own general contractor, according to the National Association of Home Builders.
How do construction loans work?
A construction loan is short-term financing that covers the build, usually with interest-only payments during construction. Once the home is complete, it typically converts to a regular mortgage or gets paid off by one.
Ready to Start Your Custom Home Build?
Let’s talk about your lot and your plan. Contact River Hills Homes or call (830) 643-0501 to schedule a free consultation. You may also want to read how long a custom home takes and what a custom home costs per square foot.
River Hills builds custom homes in New Braunfels, Canyon Lake, Wimberley, Driftwood, Dripping Springs and Spicewood.